Standard commissioning process
- Mount panel into the kiosk or suitable housing location supplied / identified by others.
- Drop draw cords down the 110mm cable duct already installed by others.
- Lower the pumps down the guide rails onto the pedestals and ensure correct position.
- Pull through the float and pump cables, if a cable extension is needed, this is extended within the chamber via a junction box and pulled through with a multicore cable.
- Take a electricity supply from a type C32 rotary isolator at the location of the panel.
- Connect the power to the control panel along with the 2 pump cables and the 4 control float cables.
- Set floats are the required heights to correspond with the inlet level.
- Fill the pump station if not already full.
- Power up the control panel and turn each pump into manual using the dials to amp test each pump and set the Lmax overload setting.
- Set the dials to auto and continue to fill to test standard operation
- Remove air locks if necessary
- Check duty assist and high level alarm function
- Leave the system in full working order